OpenProject/Ticket relation: Unterschied zwischen den Versionen
Die Seite wurde neu angelegt: „=Introduction= *Relations between work packages are used to give a ''Hierarchical structure'' to the work packages“ |
K Dirkwagner verschob die Seite OpenProject:Ticket relation nach OpenProject/Ticket relation, ohne dabei eine Weiterleitung anzulegen: Textersetzung - „OpenProject:“ durch „OpenProject/“ |
||
(17 dazwischenliegende Versionen von 2 Benutzern werden nicht angezeigt) | |||
Zeile 1: | Zeile 1: | ||
=Introduction= | =Introduction= | ||
*Relations between work packages are used to give a '' | *Relations between work packages are used to give a '''timely relation''' to the work packages | ||
**''Follows or proceeds, blocked by, part of, etc.'' | |||
*Hierarcies indicate any functional or timely relation: | |||
**''Parent-Child relation'' | |||
=Work package relations= | |||
*Work package relations indicate that work packages address a similar topic or create status dependencies. | |||
*To create a relationship between two work packages: | |||
#Select a work package, click on Relations to open the relations tab and click the + Create new relations link. | |||
#Select the type of relationship from the dropdown menu. | |||
#Enter the ID or name of the work package, to which the relation should be created and choose an entry from the dropdown menu. | |||
[[Datei:Relation.png|mini|ohne|Relations between Work Packages are useful to establish a time schedule for every task]] | |||
*You can select one of the following relations: | |||
**'''Related to''' – This option adds a link from the work package A to work package B, so that project members can immediately see the connection, even if the work packages are not members of the same hierarchy. There is no additional effect. | |||
**'''Duplicates / Duplicated by''' – This option indicates that the work package A duplicates a work package B in one way or another, for example both address the same task. This can be useful if you have the same work package that needs to be a part of a closed and public projects at the same time. The connection in this case is semantic, the changes you make in work package A will need to be adapted in work package B manually. | |||
**'''Blocks / Blocked by''' – This option defines status change restrictions between two work packages. If you set a work package A to be blocking work package B, the status of work package B cannot be set to closed or resolved until the work package A is closed (in a clode meta-status). | |||
**'''Precedes / Follows''' – Defines a chronologically relation between two work packages. For example, if you set a work package A to precede a work package B, you will not be able to change the starting date of B to be earlier than the end date of A. In addition, when you move the start or due date of A, the start and due date of B will be updated as well. | |||
**'''Includes / Part of''' – Defines if work package A includes or is part of work package B. This relation type can be used for example when you have a rollout work package and work packages which should be shown as included without using hierarchical relationships. There is no additional effect. | |||
**'''Requires / Required by''' – Defines if work package A requires or is required by work package B. There is no additional effect. | |||
=Work package hierarchies= | |||
*Work packages can be structured hierarchically, e.g. in order to break down a large work package into several smaller tasks. | |||
**''This means that there’s a parent work package that has at least one child work package.'' | |||
==Adding a Child work package== | |||
#Open a work package and select the tab Relations. | |||
#Click on + Create new child to create a child work package. | |||
##''Alternatively, you can assign an existing child work package with + Add existing child.'' | |||
[[Datei:Child.png|mini|ohne|Here you can create a new package as a child or assign an existing package as the current package's child]] | |||
*Insert the name of the new work package and save the newly created work package by pressing Enter. | |||
[[Datei:Children.png|mini|ohne|Insert the new child package name]] | |||
==Change the parent work package== | |||
*To edit or remove the parent of a work package open the work package. | |||
*At the top of the details view of the work package you will see the work package hierarchy. | |||
*Click on the Edit or delete icon to change the work package parent. | |||
[[Datei:Parent.png|mini|ohne|In any work package you can set a new parent or delete the current relation in this field]] | |||
[[Kategorie:OpenProject]] |
Aktuelle Version vom 28. März 2023, 10:02 Uhr
Introduction
- Relations between work packages are used to give a timely relation to the work packages
- Follows or proceeds, blocked by, part of, etc.
- Hierarcies indicate any functional or timely relation:
- Parent-Child relation
Work package relations
- Work package relations indicate that work packages address a similar topic or create status dependencies.
- To create a relationship between two work packages:
- Select a work package, click on Relations to open the relations tab and click the + Create new relations link.
- Select the type of relationship from the dropdown menu.
- Enter the ID or name of the work package, to which the relation should be created and choose an entry from the dropdown menu.
- You can select one of the following relations:
- Related to – This option adds a link from the work package A to work package B, so that project members can immediately see the connection, even if the work packages are not members of the same hierarchy. There is no additional effect.
- Duplicates / Duplicated by – This option indicates that the work package A duplicates a work package B in one way or another, for example both address the same task. This can be useful if you have the same work package that needs to be a part of a closed and public projects at the same time. The connection in this case is semantic, the changes you make in work package A will need to be adapted in work package B manually.
- Blocks / Blocked by – This option defines status change restrictions between two work packages. If you set a work package A to be blocking work package B, the status of work package B cannot be set to closed or resolved until the work package A is closed (in a clode meta-status).
- Precedes / Follows – Defines a chronologically relation between two work packages. For example, if you set a work package A to precede a work package B, you will not be able to change the starting date of B to be earlier than the end date of A. In addition, when you move the start or due date of A, the start and due date of B will be updated as well.
- Includes / Part of – Defines if work package A includes or is part of work package B. This relation type can be used for example when you have a rollout work package and work packages which should be shown as included without using hierarchical relationships. There is no additional effect.
- Requires / Required by – Defines if work package A requires or is required by work package B. There is no additional effect.
Work package hierarchies
- Work packages can be structured hierarchically, e.g. in order to break down a large work package into several smaller tasks.
- This means that there’s a parent work package that has at least one child work package.
Adding a Child work package
- Open a work package and select the tab Relations.
- Click on + Create new child to create a child work package.
- Alternatively, you can assign an existing child work package with + Add existing child.
- Insert the name of the new work package and save the newly created work package by pressing Enter.
Change the parent work package
- To edit or remove the parent of a work package open the work package.
- At the top of the details view of the work package you will see the work package hierarchy.
- Click on the Edit or delete icon to change the work package parent.